To give an update on the project: tomorrow, 10/17/23, we are scheduled to begin milling operations. This will require the intersection be operated under flagger control for extended periods throughout the day. We will try to keep this to a minimum and let the signals handle the majority of the work, but we do expect backups and delays. Please advise emergency services so that responses can be coordinated accordingly. We are tentatively scheduled for final base course binder Wednesday 10/18 and leveling binder 10/19. Final surfacing is scheduled for the week of 10/23/23. All paving days will require the intersection to be under flagger control. Unfortunately, paving is very weather dependent so our schedule can change daily. That being said, I will provide an update should days get moved or changed. |